Approve Acceptance of Project for Roof Replacement at Mango and Robinson Elementary Schools and Turkey Creek Middle School | |
EXECUTIVE SUMMARY | |
Elements, Inc. was selected from the approved Continuing Services Consultants list to provide design services. On May 18, 2010, the Board awarded the contract for construction to R.F. Lusa & Sons Sheetmetal, Inc. The scope of work provided for replacement of the selected roof areas at Mango and Robinson Elementary Schools and Turkey Creek Middle School. The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance. |
|
STRATEGIC OBJECTIVES | |
• Construct and maintain facilities that create an environment conducive to teaching and learning | |
FINANCIAL IMPACT (Budgeted: Yes) | |
This item was included in the District Capital Outlay: Local Millage. Contract Status: Contract Sum: $644,870.00 Approved Change Orders: $206,802.69 Credit (See Attachment) Revised Contract Sum: $438,067.31 Payments to Date: $367,983.00 Balance Due: $70,084.31 Revised Construction Cost: $599,830.51 Required Substantial Completion Date: September 15, 2010 Substantial Completion Date: September 15, 2010 |
|
EVALUATION | |
SUBMITTED BY: Hung Pham, Project Coordinator |
Rory Salimbene | Cathy L. Valdes | |
General Manager of Construction (813) 272-4112 |
Chief Facilities Officer (813) 272-4004 |
|
A 6.10e | ||