Facilities
Action Item |
DATE: | Tuesday, February 22, 2011 |
TO: | School Board Members |
FROM: | MaryEllen Elia, Superintendent |
SUBJECT / RECOMMENDATIONS | |
Approve Change Order No. 2 for High Stakes Testing Labs (Phase 2: Areas 1 and 2) |
|
EXECUTIVE SUMMARY | |
To support implementation of computer-based high stakes testing, the District is converting one or two classrooms at each school to a High Stakes Testing Lab. Modification of electrical, data, and heating, ventilating, and air conditioning (HVAC) systems associated with each lab is needed to support the classroom conversion. Staff has planned to accomplish the work in three phases, with the work in each phase divided into two projects. This project accomplishes a portion of the lab installations included in the second phase. This change order provides for final reconciliation of the Direct Purchase Program. |
|
STRATEGIC OBJECTIVES | |
• Construct and maintain facilities that create an environment conducive to teaching and learning | |
FINANCIAL IMPACT (Budgeted: Yes) | |
This item is being funded by ARRA (American Recovery and Reinvestment Act). Contract Status: Guaranteed Maximum Price: $1,430,662.00 Approved Change Order: $150,000.00 Credit (See Attachment) Change Order Recommended Herein: $104,741.70 Extra Revised Guaranteed Maximum Price: $1,385,403.70 Revised Construction Cost: $1,427,958.70 Required Substantial Completion Date: November 5, 2010 |
|
EVALUATION | |
SUBMITTED BY: Alice Sutton, Project Coordinator |
Rory Salimbene | Cathy L. Valdes | |
General Manager of Construction (813) 272-4112 |
Chief Facilities Officer (813) 272-4004 |
|
A 6.07 | ||
Hillsborough County Public Schools (Florida) * Mtg.#20110222_454 (Board Meeting) * Section A Item# 6.07 |