Action Item
DATE: Tuesday, May 17, 2011
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
Approve Acceptance of Project for Steinbrenner High School, New Facility
EXECUTIVE SUMMARY

On July 26, 2005, the Board appointed HCBeck, Ltd. to provide construction management services. This new facility, which opened in August 2009, was a reuse of the Middleton High School design and relieved overcrowding at Alonso, Gaither, and Sickles High Schools.

The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

STRATEGIC OBJECTIVES
• Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)

This item was included in the District Capital Outlay: Certificates of Participation Series 2004C ($8,054,496) and 2006 ($39,035,771).

Contract Status:
Guaranteed Maximum Price: $47,090,267.00
Approved Change Orders: $13,469,937.51 Credit (See Attachment)
Revised Guaranteed Maximum Price: $33,620,329.49
Payments to Date: $33,437,521.76
Balance Due: $182,807.73
Revised Construction Cost: $45,162,919.89

Required Substantial Completion Date: July 30, 2009
Substantial Completion Date: July 30, 2009

EVALUATION
SUBMITTED BY:  John Williams, Project Coordinator
Rory Salimbene   Cathy L. Valdes
General Manager of Construction
(813) 272-4112
  Chief Facilities Officer
(813) 272-4004
    A 6.06
Hillsborough County Public Schools (Florida) * Mtg.#20110517_459 (Board Meeting) * Section A Item# 6.06