SUBJECT / RECOMMENDATIONS | |
Approve Acceptance of Project for Roof Replacement at Mann Middle School | |
EXECUTIVE SUMMARY | |
On October 20, 2009, the Board appointed the engineering firm of Weber and Tinnen, PA to provide design services. On May 18, 2010, the Board awarded the contract for construction to Quality Roofing, Inc. The scope of work provided for roof, edge metal, and roof drain replacement on selected buildings. |
|
STRATEGIC OBJECTIVES | |
• Construct and maintain facilities that create an environment conducive to teaching and learning | |
FINANCIAL IMPACT (Budgeted: Yes) | |
This item was included in the District Capital Outlay: Local Millage. Contract Status: Required Substantial Completion Date: August 13, 2010 |
|
EVALUATION | |
SUBMITTED BY: Hung Pham, Project Coordinator |
Rory Salimbene | Cathy L. Valdes | |
General Manager of Construction (813) 272-4112 |
Chief Facilities Officer (813) 272-4004 |
|
A 6.08b | ||