HCPS FL Logo Facilities
Action Item
DATE: Tuesday, August 16, 2011
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
Approve Design Development Phase for Modular Installation and Interior Renovation at Learey Technical Center and Remodeling of Existing Modulars at Gary Adult High School
EXECUTIVE SUMMARY

As part of a District-wide reconfiguration of adult education programs, District staff plans to establish a new Adult Education Administrative Center, CARIBE facility and postsecondary student services center at Learey Technical Center; and add GED and CREDIT adult teen programs at Gary Adult High School. To facilitate these programs, modular building additions and remodeling are required.

District staff combined the adult program modular requirements at Learey and Gary into a single project for execution. Staff selected Long & Associates Architects/Engineers and Halfacre Construction Company from the approved continuing services consultants list to provide design and construction management services. The scope of work provides for the addition and interior modification of a twelve unit modular facility for the Adult Education Administrative Center and CARIBE requirements at Learey Technical Center; minor modifications of the permanent facility at Learey to create a testing materials storage vault and a remodeled reception area for the post-secondary student services center; and modification of 11 administrative modulars at Gary Adult High School to provide classrooms, computer labs and administrative facilities supporting the new adult teen programs.

Project completion is scheduled for September 30, 2011.

Approval of the Design Development Phase will allow the architect to proceed with construction documents.

STRATEGIC OBJECTIVES
• Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  No)

Construction cost is warranted at $750,000. The construction budget is $750,000. This item is included in the District Capital Outlay: Community Investment Tax and Land Proceeds, and Workforce funding.

EVALUATION
SUBMITTED BY:  Jill Edwards, Project Coordinator
Rory Salimbene   Cathy L. Valdes
General Manager of Construction
(813) 272-4112
  Chief Facilities Officer
(813) 272-4004
    A 6.05
Hillsborough County Public Schools (Florida) * Mtg.#20110816_469 (Board Meeting) * Section A Item# 6.05