Facilities
Action Item |
DATE: | Tuesday, February 14, 2012 |
TO: | School Board Members |
FROM: | MaryEllen Elia, Superintendent |
SUBJECT / RECOMMENDATIONS | |
Approve Design Development Phase for Heating, Ventilating, and Air Conditioning (HVAC) Renovation at Hunter's Green Elementary School | |
EXECUTIVE SUMMARY | |
A previously approved District Five Year Plan provides for renovation of the HVAC system at Hunter's Green Elementary School. District staff selected KPI Engineering, Inc. from the approved Continuing Services Consultants list to provide design services. Project completion is scheduled for August 2012. Approval of the Design Development Phase will allow the engineer to proceed with construction documents. |
|
STRATEGIC OBJECTIVES | |
• Construct and maintain facilities that create an environment conducive to teaching and learning | |
FINANCIAL IMPACT (Budgeted: Yes) | |
Total funds in the amount of $1,989,000 are included in the District Capital Outlay: Local Millage. The estimate of probable cost is $1,988,685. |
|
EVALUATION | |
SUBMITTED BY: John Williams, Project Coordinator |
Rory Salimbene | Cathy L. Valdes | |
General Manager of Construction (813) 272-4112 |
Chief Facilities Officer (813) 272-4004 |
|
A 6.03 | ||