Approve Construction Documents and Guaranteed Maximum Price for Roof Replacement at Chiaramonte Elementary School | |
EXECUTIVE SUMMARY | |
A previously approved District Five Year Plan provides for replacement of the roof at Chiaramonte Elementary School. District staff selected Wilder Architecture, Inc. and Horus Construction Services, Inc. from the approved Continuing Services Consultants list to provide design and construction management services. Project completion is scheduled for August 20, 2012. Approval of the Guaranteed Maximum Price (GMP) will establish the cost for the project. |
|
STRATEGIC OBJECTIVES | |
• Construct and maintain facilities that create an environment conducive to teaching and learning | |
FINANCIAL IMPACT (Budgeted: Yes) | |
Construction cost is warranted at $1,379,686. The construction budget is $1,380,000. This item is included in the District Capital Outlay: Local Millage. |
|
EVALUATION | |
SUBMITTED BY: Alice Sutton, Project Coordinator |
Rory Salimbene | Cathy L. Valdes | |
General Manager of Construction (813) 272-4112 |
Chief Facilities Officer (813) 272-4004 |
|