Approve Award of Contract for Painting and Water Intrusion Correction at Mintz Elementary School
EXECUTIVE SUMMARY

A previously approved District Five Year Plan provides for interior and exterior painting at Mintz Elementary School.  The scope of work also provides for building envelope repairs to eliminate water intrusion.

District staff selected Jerel McCants Architecture, Inc. from the approved Continuing Services Consultants list to provide design services.

The project was advertised and bids received (see attached bid tabulation). Award of the contract for construction to the low bidder, Kimszal Contracting, Inc. is recommended.

STRATEGIC OBJECTIVES
• Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)

Total funds in the amount of $431,000 are included in the District Capital Outlay: Millage.  The contract amount being awarded is $430,300.

EVALUATION
SUBMITTED BY:  Hung Pham, Project Coordinator
Rory Salimbene   Cathy L. Valdes
General Manager of Construction
(813) 272-4112
  Chief Facilities Officer
(813) 272-4004