HCPS FL Logo Facilities
Action Item
DATE: Tuesday, October 9, 2012
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
Approve Acceptance of Project for Renovation (Phase 2) at Armwood High School
EXECUTIVE SUMMARY

The Board previously appointed Ranon & Partners, Inc. Architects and Ellis Construction Company, Inc. to provide design and construction management services for the renovation of Armwood High School. The renovation provided for correction of code and safety deficiencies; roof replacement; replacement of data, closed circuit television (CCTV), fire alarm, intercom, and heating, ventilating, and air conditioning (HVAC) systems; new signage, ceiling tiles, lighting, and flooring; repair or replacement of damaged casework; upgrades to existing electrical and security systems; interior repainting; repair, cleaning, and sealing of exterior brick, and repainting of other exterior surfaces; restroom and kitchen renovations; new stadium lighting and sound systems; new playcourts; replacement of auditorium seating; and limited replacement of instructional aids.

The renovation was planned in phases. Phase 1, which included the building exterior renovation and replacement of the roof, chiller plant, and field lighting and sound systems, was previously accepted by the Board. Phase 2 addressed the remaining scope.

The architect advises that Phase 2 of the renovation is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

STRATEGIC OBJECTIVES
• Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)
This item was included in the District Capital Outlay: Certificate of Participation Series 2004C ($11,000,000) and Local Millage ($8,907,969).
Contract Status:
Guaranteed Maximum Price: $19,907,969.00
Change Orders Approved: $4,644,772.40 Credit (See Attachment)
Revised Guaranteed Maximum Price: $15,263,196.60
Payments to Date: $15,161,513.91
Balance Due:  $101,682.69
Revised Construction Cost: $20,451,273.30
Contract Completion Date: July 11, 2011
Substantial Completion Date:  July 07, 2011
EVALUATION
SUBMITTED BY:  Alice Sutton, Project Coordinator
Rory Salimbene   Cathy L. Valdes
Manager of Planning & Construction
(813) 272-4112
  Chief Facilities Officer
(813) 272-4004
    A 6.05