Action Item
DATE: Tuesday, December 11, 2012
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS

Approve Acceptance of Project for Modular Addition and Remodeling at Brewster Adult School

EXECUTIVE SUMMARY

On May 3, 2011, the Board approved the use of Community Investment Tax proceeds for replacement of obsolete and non-economically repairable portable facilities with modular buildings. Replacement of obsolete portables at Brewster Adult School was required. To reduce the number of modular buildings required for replacement, remodeling of the space vacated by the relocation of GED program activities to Gary Adult High School was needed in conjunction with the portable replacement.

District staff combined the portable demolition, modular installation and permanent building remodeling at Brewster into a single project and selected Long & Associates Architects/Engineers, Inc. and Halfacre Construction Company from the approved Continuing Services Consultants list to provide design and construction management services. The scope of work provided for disconnection and demolition of 13 portables and an associated walkway, and site work and utility connections for ten classroom modulars and two gang restrooms at Brewster. Remodeling of Room 203 and adjacent areas on the second floor of Building 1 at Brewster into two classrooms and an exit corridor,  included replacement of the existing egress stair with a new stairwell, and was also included in the project scope.

The design professional has certified that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

STRATEGIC OBJECTIVES
• Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)

This item was included in the Workforce Funding and District Capital Outlay: Community Investment Tax (CIT).

Contract Status:
Guaranteed Maximum Price:  $872,348.00
Approved Change Orders:  $139,214.86 Credit (See Attachment)
Revised Guaranteed Maximum Price:  $733,133.14
Payments to Date:  $724,558.14
Balance Due:  $8,575.00
Revised Construction Cost:  $760,842.14

Required Substantial Completion Date:  February 27, 2012
Approved Time Extension:  35 Calendar Days
Revised Required Substantial Completion Date:  April 2, 2012
Substantial Completion Date:  April 2, 2012

EVALUATION
SUBMITTED BY:  Jill Edwards, Project Coordinator
Rory Salimbene   Cathy L. Valdes
General Manager of Construction
(813) 272-4112
  Chief Facilities Officer
(813) 272-4004