HCPS FL Logo Facilities
Action Item
DATE: Tuesday, February 19, 2013
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
Approve Acceptance of Project for Roof Replacement at Hill Middle School
EXECUTIVE SUMMARY

On  October  26,  2010,  the  Board  approved  the issuance of approximately  $37,935,000  of  Qualified  School Construction Bonds (QSCBs) for renovation of roofs and heating, ventilating, and air conditioning (HVAC) systems at various District sites.   The  QSCBs provided for acceleration of roof and HVAC renovations  previously scheduled in the  District Facilities Five Year Work Program.   The  roof renovations are being  executed in phases to  avoid  over-tasking available roofing contractors and ensure competitive pricing.  (QSCB funded projects are indicated in the attachment.)

District staff selected C.B. Goldsmith  and Associates, Inc. and Walbridge  Aldinger  Company  from the approved Continuing Services Consultants list to provide design and construction management services to replace the roof at Hill Middle School.   

The design professional has certified that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

STRATEGIC OBJECTIVES
• Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)
This item was included in the District Capital Outlay: Qualified School Construction Bonds.

Contract Status:
Guaranteed Maximum Price:  $1,429,590.00
Approved Change Orders:  $480,219.91 Credit (See Attached)
Revised Guaranteed Maximum Price:  $949,370.09
Payments to Date:  $901,901.59
Balance Due:  $47,468.50
Revised Construction Cost:  $1,362,432.41

Required Substantial Completion Date:  September 28, 2011
Approved Time Extension:  43 Calendar Days
Revised Required Substantial Completion Date:  November 10, 2011
Substantial Completion Date:  November 10, 2011
EVALUATION
SUBMITTED BY:  John Williams, Project Coordinator
Rory Salimbene   Cathy L. Valdes
General Manager of Construction
(813) 272-4112
  Chief Facilities Officer
(813) 272-4004
    A 6.04c