DATE: Tuesday, May 7, 2013
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
Approve Acceptance of Project for 2012 Modular Installations at Multiple Sites
EXECUTIVE SUMMARY

District staff combined requirements for replacement of obsolete and non-economically repairable portable facilities with modular buildings at multiple sites into a single project and selected The Architectural Practice, Inc. and Halfacre Construction Company from the approved Continuing Services Consultants list to provide design and construction management services.  The scope of work provided for portable demolition, site preparation and utility connections of modular clinics and classrooms at nine sites, and portable demolition only at four additional sites.   (See attached list)

The design professional has certified that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

STRATEGIC OBJECTIVES
• Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)
This item was included in the District Capital Outlay: Land Proceeds.

Contract Status:
Original Contract Amount:  $1,470,770.00
Approved Change Orders:  $285,308.35 Credit (See Attachment)
Revised Contract Amount:  $1,185,461.65
Payments to Date:  $1,124,106.92
Balance Due:  $61,354.73
Revised Construction Cost:  $1,514,729.00

Required Substantial Completion Date:  August 12, 2012
Approved Time Extension:  8 Calendar Days
Revised Required Substantial Completion Date:  August 20, 2012
Substantial Completion Date:  August 20, 2012
EVALUATION
SUBMITTED BY:  Jill Edwards, Project Coordinator
Rory Salimbene   Cathy L. Valdes
General Manager of Construction
(813) 272-4112
  Chief Facilities Officer
(813) 272-4004
    A 7.03
Hillsborough County Public Schools (Florida) * Mtg.#20130507_561 (Board Meeting) * Section A Item# 7.03