Action Item
DATE: Tuesday, October 8, 2013
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
Approve Acceptance of Project for Roof Replacement at 2 Sites (Grady Elementary School and LaVoy Exceptional Center)
EXECUTIVE SUMMARY

On October 26, 2010, The Board approved the issuance of approximately $37,935,000 of Qualified School Construction Bonds (QSCBs) for renovation of roofs and heating, ventilating and air conditioning (HVAC) systems at  various  District sites. The QSCBs provided  for  acceleration  of  roof  and HVAC  renovations  previously scheduled in the District Facilities Five Year Work Program. The roof renovations were executed in phases to avoid over-tasking available roofing contractors and ensure competitive pricing. (QSCB funded projects are indicated in the attachment.) 

District staff combined requirements for replacement of a portion of the roofs at Grady Elementary School and LaVoy Exceptional Center into a single project and selected C. B. Goldsmith and Associates, Inc. from the approved Continuing Services Consultants list to provide design services.  On November 13, 2012, Southern Roofing Co. was awarded the contract.

The design professional has certified that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

STRATEGIC OBJECTIVES
• Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)
This project was included in the District Capital Outlay: Qualified School Construction Bonds.

Contract Status:
Original Contract Amount:  $1,213,291.00
Approved Change Orders:  $498,047.85 Credit
Revised Contract Amount:  $715,243.15
Payments to Date:  $626,643.79
Balance Due:  $88,599.36
Revised Construction Cost:  $1,139,950.27

Required Substantial Completion Date:  May 14, 2013
Approved Time Extension:  7 Calendar Days
Revised Required Substantial Completion Date:  May 21, 2013
Substantial Completion Date:  May 21, 2013
EVALUATION
SUBMITTED BY:  Alice Sutton, Project Coordinator
Rory Salimbene   Cathy L. Valdes
General Manager of Construction
(813) 272-4112
  Chief Facilities Officer
(813) 272-4004
    A 7.03