HCPS FL Logo Facilities
Action Item
DATE: Tuesday, April 29, 2014
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
Approve Acceptance of Project for Door and Hardware Replacement at Dowdell Middle and Forest Hills Elementary Schools
EXECUTIVE SUMMARY

A previously approved District Facilities Five Year Work Program provided for replacement of doors and door hardware at Dowdell Middle School and Forest Hills Elementary School.  District staff combined the requirements into a single project and selected Jerel McCants Architecture, Inc. to provide design services.  On May 21, 2013, the Board awarded the contract for construction to New Vista Builders Group, LLC.

The design professional has certified that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

STRATEGIC OBJECTIVES
• Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)

This item was included in the District Capital Outlay:  Local Millage.

Contract Status:
Contract Sum:  $513,750.00
Approved Change Orders:  $252,705.64 Credit  (See Attachment)
Revised Contract Sum:  $261,044.36
Payments to Date:  $237,264.25
Balance Due:  $23,780.11
Revised Construction Cost:  $496,983.50

Required Substantial Completion Date:  August 9, 2013
Approved Time Extension:  164 Calendar Days
Revised Required Substantial Completion Date:  January 20, 2014
Substantial Completion Date:  January 20, 2014

EVALUATION
SUBMITTED BY:  Alice Sutton, Project Manager
Rory A. Salimbene   Christopher Farkas
General Manager of Construction
(813) 272-4112
  Chief Facilities Officer
(813) 272-4004
    A 7.11
Hillsborough County Public Schools (Florida) * Mtg.#20140429_631 (Board Meeting) * Section A Item# 7.11