Action Item
DATE: Tuesday, June 24, 2014
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
Approve Design Development for Classroom Addition at Lennard High School
EXECUTIVE SUMMARY

A 20-classroom addition is proposed for Lennard High School to alleviate overcrowding at East Bay High School and assist in accommodating growth impacting Riverview and Lennard High Schools. The addition will open in August 2015 for the 2015-2016 school year.

On April 29, 2014, the Board appointed Holmes Hepner & Associates Architects, Inc., the designer of record for Lennard High School, to provide the needed design services.

Approval of design development as illustrated in the attachment will allow the design professional to proceed with construction documents.

STRATEGIC OBJECTIVES
• Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  Yes)

The construction budget is $3,850,000, to be funded by Impact Fees.

EVALUATION
SUBMITTED BY:  Jill Edwards, Project Coordinator
Rory A. Salimbene   Christopher Farkas
General Manager of Construction
(813) 272-4112
  Chief Facilities Officer
(813) 272-4004
    A 7.04
Hillsborough County Public Schools (Florida) * Mtg.#20140624_635 (Board Meeting) * Section A Item# 7.04