Action Item
DATE: Tuesday, February 3, 2015
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS

Approve Acceptance of Project for Roof Replacement at Young Middle School

EXECUTIVE SUMMARY

A previously approved District Facilities Five Year Work Program provided for replacement of the roof at Young Middle School.  The scope of work included removal and replacement of the existing roof on most of the campus.

District staff selected Weber & Tinnen, P.A. from the approved Continuing Services Consultants list to provide design services.  On February 25, 2014, the Board awarded a contract for construction to Roof USA.

The design professional has certified that the work is complete in accordance with the plans and specifications and other contract documents and recommends Board Acceptance.

STRATEGIC OBJECTIVES
• Construct and maintain facilities that create an environment conducive to teaching and learning
FINANCIAL IMPACT (Budgeted:  No)

This item is included in the District Capital Outlay:  Local Millage.

Contract Status:
Contract Sum:  $1,087,740.00
Approved Change Orders: $481,168.13  Credit (See Attachment)
Revised Contract Sum:  $606,571.87
Payments to Date:  $576,243.28
Balance Due:  $30,328.59
Revised Construction Cost:  $982,459.70

Required Substantial Completion Date:  June 28, 2014
Substantial Completion Date:  June 28, 2014

EVALUATION
SUBMITTED BY:  Alice Sutton, Project Coordinator
Rory A. Salimbene   Christopher Farkas
General Manager of Construction
(813) 272-4112
  Chief Facilities Officer
(813) 272-4004