Operations
Action Item |
DATE: | Tuesday, May 24, 2016 |
TO: | School Board Members |
FROM: | Jeff Eakins, Superintendent |
SUBJECT / RECOMMENDATIONS | |
Approve Acceptance of Project for Roof Replacement at Riverview Elementary School |
|
EXECUTIVE SUMMARY | |
A previously approved District Facilities Five Year Work Program provided for replacement of a portion of the roof at Riverview Elementary School. The scope of work included removal and replacement of selected roof areas at the school. District Staff selected Roof Engineering Associates, Inc. from the approved Continuing Services Consultants list to provide design services. On March 3, 2015, the Board awarded a contract for construction to Roof USA, LLC. |
|
STRATEGIC OBJECTIVES | |
• Demonstrate best financial practices • Construct and maintain facilities that create an environment conducive to teaching and learning | |
FINANCIAL IMPACT (Budgeted: Yes) | |
Funds in the amount of $610,166.43 will be available in the Local Millage fund. For tracking purposes, the project number specific to this agenda item is 8138. As of Thursday, May 5, 2016, the remaining balance less encumbrances for this line item equaled $26,000.31.
Contract Sum: $568,523.00 |
|
EVALUATION | |
SUBMITTED BY: Hung Pham, Project Coordinator |
Rory A. Salimbene | Christopher Farkas | |
General Manager of Construction (813) 272-4112 |
Chief Operating Officer (813) 272-4004 |
|
C 7.07 | ||
Hillsborough County Public Schools (Florida) * Mtg.#20160524_761 (Board Meeting) * Section C Item# 7.07 |